§60.5175 - How do I establish operating limits if I do not use a wet scrubber, fabric filter, electrostatic precipitator, activated carbon injection, or afterburner, or if I limit emissions in some other manner, to comply with the emission limits?
Title 40 | STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES
part_subject: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES (CONTINUED)"
subpart_code: "M"
subpart_subject: "MMM—Emission Guidelines and Compliance Times for Existing Sewage Sludge Incineration Units"
section_number: "60.5175"
section_subject: "How do I establish operating limits if I do not use a wet scrubber, fabric filter, electrostatic precipitator, activated carbon injection, or afterburner, or if I limit emissions in some other manner, to comply with the emission limits?"
cfr_reference: "40 CFR 60.5175"
title_name: "Title 40"
title_subject: "Protection of Environment"
parts_covered: "Part 60 (§ 60.500 to end of part 60 sections)"
revised_date: "Revised as of July 1, 2019"
publication_date: "As of July 1, 2019"
contains_description: "Containing a codification of documents of general applicability and future effect"
publication_info: "Published by the Office of the Federal Register National Archives and Records Administration as a Special Edition of the Federal Register"
---
If you use an air pollution control device other than a wet scrubber, fabric filter, electrostatic precipitator, activated carbon injection, or afterburner, or limit emissions in some other manner (e.g., materials balance) to comply with the emission limits in § 60.5165, you must meet the requirements in paragraphs (a) and (b) of this section.
(a)Meet the applicable operating limits and requirements in § 60.4850, and establish applicable operating limits according to § 60.5190.
(b)Petition the Administrator for specific operating parameters, operating limits, and averaging periods to be established during the initial performance test and to be monitored continuously thereafter.
(1)You are responsible for submitting any supporting information in a timely manner to enable the Administrator to consider the application prior to the performance test. You must not conduct the initial performance test until after the petition has been approved by the Administrator, and you must comply with the operating limits as written, pending approval by the Administrator. Neither submittal of an application, nor the Administrator's failure to approve or disapprove the application relieves you of the responsibility to comply with any provision of this subpart.
(2)Your petition must include the five items listed in paragraphs (b)(2)(i) through (b)(2)(v) of this section.
(i)Identification of the specific parameters you propose to monitor.
(ii)A discussion of the relationship between these parameters and emissions of regulated pollutants, identifying how emissions of regulated pollutants change with changes in these parameters, and how limits on these parameters will serve to limit emissions of regulated pollutants.
(iii)A discussion of how you will establish the upper and/or lower values for these parameters that will establish the operating limits on these parameters, including a discussion of the averaging periods associated with those parameters for determining compliance.
(iv)A discussion identifying the methods you will use to measure and the instruments you will use to monitor these parameters, as well as the relative accuracy and precision of these methods and instruments.
(v)A discussion identifying the frequency and methods for recalibrating the instruments you will use for monitoring these parameters.