part_subject: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES (CONTINUED)"
subpart_code: "D"
subpart_subject: "DDD—Emissions Guidelines and Compliance Times for Commercial and Industrial Solid Waste Incineration Units"
section_number: "60.2706"
section_subject: "By what date must I conduct the initial air pollution control device inspection?"
cfr_reference: "40 CFR 60.2706"
title_name: "Title 40"
title_subject: "Protection of Environment"
parts_covered: "Part 60 (§ 60.500 to end of part 60 sections)"
revised_date: "Revised as of July 1, 2019"
publication_date: "As of July 1, 2019"
contains_description: "Containing a codification of documents of general applicability and future effect"
publication_info: "Published by the Office of the Federal Register National Archives and Records Administration as a Special Edition of the Federal Register"
---
(a)The initial air pollution control device inspection must be conducted within 60 days after installation of the control device and the associated CISWI reaches the charge rate at which it will operate, but no later than 180 days after the final compliance date for meeting the amended emission limitations.
(b)Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless the owner or operator obtains written approval from the state agency establishing a date whereby all necessary repairs of the designated facility must be completed.