part_subject: "STANDARDS OF PERFORMANCE FOR NEW STATIONARY SOURCES (CONTINUED)"
subpart_code: "B"
subpart_subject: "BBB—Emission Guidelines and Compliance Times for Small Municipal Waste Combustion Units Constructed on or Before August 30, 1999"
section_number: "60.1705"
section_subject: "What emission limits must I meet? By when?"
cfr_reference: "40 CFR 60.1705"
title_name: "Title 40"
title_subject: "Protection of Environment"
parts_covered: "Part 60 (§ 60.500 to end of part 60 sections)"
revised_date: "Revised as of July 1, 2019"
publication_date: "As of July 1, 2019"
contains_description: "Containing a codification of documents of general applicability and future effect"
publication_info: "Published by the Office of the Federal Register National Archives and Records Administration as a Special Edition of the Federal Register"
---
(a)After the date the initial stack test and continuous emission monitoring system evaluation are required or completed (whichever is earlier), you must meet the applicable emission limits specified in the four tables of this subpart:
(1)For Class I units, see tables 2 and 3 of this subpart.
(2)For Class II units, see table 4 of this subpart.
(3)For carbon monoxide emission limits for both classes of units, see table 5 of this subpart.
(b)If your Class I municipal waste combustion unit began construction, reconstruction, or modification after June 26, 1987, then you must comply with the dioxins/furans and mercury emission limits specified in table 2 of this subpart as applicable by the later of the following two dates:
(1)One year after the effective date of State plan approval.
(2)One year after the issuance of a revised construction or operating permit, if a permit modification is required. Final compliance with the dioxins/furans limits must be achieved no later than December 6, 2005, even if the date 1 year after the issuance of a revised construction or operation permit is later than December 6, 2005.